Written by Albert Szakacs, Capacity & MTM specialist in automotive manufacturing and founder of OptiLoad Smart. Updated 2026-11-28.

"Send me a recovery plan by Friday." When a plant falls behind, management wants two answers: when will we be back on track, and what will it cost. This guide shows a four-step method that gives both, on a worked example for a whole plant.

The example plant

15 production lines, 3 shifts a day, 5 working days a week, 8-hour shifts. After a difficult quarter the plant is behind on 40 part numbers. All figures below are for the whole plant, all 15 lines together.

BacklogWhole plant
Late units2,109,705
Line time needed to recover252.5 shifts
Part numbers affected40
Lines involved15

Step 1: measure the backlog in shifts, not units

Units are what the customer ordered; shifts are what the plant has to spend. Convert every late part into line time with its own cycle time on its own line.

Backlog shifts = Σ (late units × cycle time) ÷ (shift length × OEE)

In the example, MODEL-B-004 is only 2% of the late units but 6% of the line time needed. Ranked by units it sits near the bottom of the list; ranked by shifts it is one of the real problems.

Step 2: rank recovery levers by the capacity they return

Normal capacity of the plant is 15 lines × 3 shifts × 5 days = 225 shifts per week. Each lever is expressed in the same unit, so they can be compared honestly.

LeverExtra shifts / weekCatch
Saturday + Sunday, 3 shifts+90Highest premium pay, fatigue after 2–3 weeks
Saturday, 3 shifts+45Needs agreement in time
OEE 75% → 85% on the late lines+30Cheap in money, slow to prove
Move volume to lines with free capacityvariesOnly where the part is approved on that line
Extend a shift 8 h → 9 h on 5 lines+9Overtime limits
Halve planned maintenance+7.5Borrowing from next month

With Saturdays only, 252.5 shifts take about 5.6 weeks to clear; with full weekends and OEE raised to 85%, about 2.1 weeks. Apply each lever only on the lines that carry the backlog: an extra Saturday on a line with no late parts returns nothing.

Step 3: decide the order, and show what it costs

Capacity is limited, so the order decides who waits. A practical rule: line-stop risk at the customer first, then contractual penalties, then the largest backlog in shifts, then due date. In the example three parts go first:

PriorityPartBacklog shiftsBack by
1MODEL-A-02256.3Week 50
2MODEL-B-01415.8Week 51
3MODEL-A-00426.1Week 53

Not everything fits in 5 weeks. The three priority parts are safe; the other 37 move behind them. Management needs to see that sentence before agreeing the plan, not three weeks later.

Recovery simulator result showing the completion week and lines used for each priority part
Recovery order, completion week per part and lines used (OptiLoad Smart recovery simulator, demo data).

Step 4: turn the weekly plan into tomorrow's load

A recovery plan that lives in a weekly report never reaches the line. For every line on the recovery list, build the next day: which parts, how many, in what order, with changeovers and breaks counted and the finish time visible. If the day does not fit, you find out the evening before.

Checklist for your next recovery meeting